This message is recorded at 11.30am Wednesday 19th June 2024.
If you require water for filling storage ponds, please contact William Tallott on 0275231295 now.
The buffer pond embankment lining project will start in approximately 2-3 weeks. You have this window available to take water to full your storage pond.
Once the Lining Works start a stock water bypass channel will be constructed to carry stock water capacity only. Lining works are expected to take 4 – 6 weeks. End of August is the expected date of completion.
Currently we are trying to keep the buffer pond level low to dry out excess silt and allow construction of the stock water bypass channel.
In summary if you need water in your storage pond order it now by contacting William Tallott on 0275231295 or wait until end of August.
Jamie Hamilton
WIL Operations Manager