Table A: Current Consents Granted by Environment Canterbury

Consent Number
Activity
Expert Date
Ongoing Monitoring
Requirements
CRC000585* Use up to 10.5m3/s from the Waimakariri River from two intakes at Browns Rock 9m3/s can be used for irrigation supply-    1.5 m3/s can be used for Eyre River recharge 18 November 2031 ·   Usage of water must be monitored
·   Fish screens at intake sites must be operating
·  
Abstraction of water shall be restricted when flow in the  Waimakariri River is less than 46.2m3/s
CRC000955 Place a pipe under the bed of the Cust River, East of Swamp Road 21 December 2001 ·   Erosion must be monitored and control works carried out as required
CRC001015 Place a pipe under the bed of the Cust River at Barkers Road 10 January 2005 None
CRC952566 Disturb the bed of the Waimakariri River in and around the Browns Rock area to create a diversion of water to the intakes of a water management scheme 18 November 2031 ·   Environment Canterbury must be notified 2 working days before bed disturbance is undertaken
·   Vehicles and machinery shall minimise their entry into river channels containing flowing water
CRC952567 Divert flow from the Waimakariri River in and around the Browns Rock area to maintain river flow at the intakes of a water management scheme 18 November 2031 None
CRC952568 Construct and use a proposed water intake structure and alter an existing water intake structure in the bed of the Waimakariri River at Browns Rock 18 November 2031 ·   Structural integrity of the works must be maintained
·   Erosion must be monitored and control works carried out as required
·  
Fish screens and fish bypass must be operating
CRC952570 Discharge water and material from a settling pond at weekly intervals onto land, into or onto the bed of the Waimakariri River and into the water of the Waimakariri River-    Discharge rate of 30m3/s for one hour per week beginning at 1.00pm on Wednesdays 18 November 2031 ·   Suspended sediment concentrations in the receiving water must not increase by more than 50grams per m3
·   Sampling shall be carried out during the discharge
·  
Notices stating the times of discharge shall be placed and maintained in the river bed  
CRC952571 Discharge up to 3m3/s of water into the Eyre River for groundwater recharge from August to May 18 November 2031 ·   Discharge cannot occur at times of high groundwater levels
·   Discharge rates must be recorded
·  
Monitor changes in groundwater levels and quality
·  
Monitor the water quality at the discharge points
·  
Consultation with landowners must be carried out regarding the results of the recharge trials
CRC952572 Construct and use a water discharge structure in the bed of the Cust River for the purpose of discharging water into the Cust River at Starvation Hill Road 18 November 2031 ·   Structural integrity of the works must be maintained
·   Erosion must be monitored and control works carried out as required
CRC952573 Construct and use a water discharge structure in the Cust Main Drain River for the purpose of discharging water into the Cust River, North of Barkers Road 18 November 2031 ·   Structural integrity of the works must be maintained
·   Erosion must be monitored and control works carried out as required
CRC952575 Construct and use a water discharge structure in the bed of the Ashley River for the purpose of discharging water into the Ashley River, South East of O’Hallorans Road 18 November 2031 ·   Structural integrity of the works must be maintained
·  
Erosion must be monitored and control works carried out as required
CRC952577 Construct and use a water race structure, being an inverted syphon, in and across the riverbed of the Cust River, West of Ngakuroa Farm 18 November 2031 ·   Structural integrity of the works must be maintained
·   Erosion must be monitored and control works carried out as required
CRC952578 Construct and use a water race structure, being an inverted syphon, in and across the bed of the Eyre River at Warren Road 18 November 2031

·   Structural integrity of the works must be maintained
·  
Erosion must be monitored and control works carried out as required

CRC010487 Disturb the bed of the Eyre River by installing a syphon under the bed of the river, South of Wolffs Road 3 November 2002 ·   Structural integrity of the works must be maintained


Table B: Consents Granted by Waimakariri District Council

Consent Number
Activity
Expiry Date
Ongoing Monitoring Requirements
RC005210 Earthworks to extend the water race to run along the roadside of Main Drive Road 24 October 2002 None
RC950293 Construct an intake structure, settling ponds, main distribution race, wetlands and discharge structures extending from the Waimakariri River to the Ashley River 18 November 2031

·   Structural integrity of the works must be maintained
·   Leakage from the system must be less than 10%
·   Check that there are no impacts on the identified woodland remnants of natural significance

 

   
   
 